How Road Changes Actually Happen
Whose road it is decides who can change it, and how
In Kansas City, Missouri, a request for a crosswalk, stop sign or speed hump starts with a call to 311.1 Traffic engineers take it from there. A crosswalk in the middle of a block usually gets approved only if at least 10 people cross there every hour for five straight weekday hours, and only where the speed limit is under 45 mph.1 The City Council can overrule the engineers, but the engineers decide first.1
The city gets about 200 traffic-calming requests a year. Clearing them would cost about $5.4 million.2
Those are Kansas City's rules for Kansas City's streets. In Beaufort, South Carolina, city leaders wanted narrower lanes and on-street parking to slow drivers down. They couldn't make the change on their own: the state owns nearly every road in town.3
A good request can stall because it went to the wrong government, or asked for the wrong kind of change. This page gives you four questions that sort out both.
Note
Reserving land for a future road, or changing local law, is covered in Legal & Planning Mechanisms.
Why requests stall
- Wrong government. The city may not own the road, or may own the pavement but not the signal. In Washington State, the state DOT runs the signals on state highways through smaller towns; larger cities run their own.4
- Wrong kind of ask. Fixing a faded stripe and adding a stop sign take different tracks. One needs a work order. The other needs a study.
- Wrong expectation. Neighborhood support starts a request. Engineers decide it.1
- Missed timing. Some changes arrive without a request. When a city resurfaces a street, federal law requires curb ramps at its crossings.5
The four questions
| Question | Why it matters |
|---|---|
| 1. What are you asking for? | Restoring, adding and changing a standard take different paths. |
| 2. Is the road public or private? | A private road answers to its owner or HOA, not a government. |
| 3. Which government has authority? | Ownership is the start. Signals, sidewalks and sovereignty can split it. |
| 4. How does that government process it? | Seven tracks, from a work order to a capital project. |
1. What are you asking for?
Restore something already there. A faded stripe, a broken sign, a pothole. The need was proven when it went in, so it doesn't need proving again.
Add or change something at one location. A new stop sign, a crosswalk, a signal change, a road diet. It's new, so someone has to justify it.
Change the standard everywhere. If the problem is the rule itself, not one street, the path runs through your local government's comprehensive plan or ordinances. See Legal & Planning Mechanisms. The rest of this page covers the first two.
2. Is the road public or private?
A private road has no government in charge of its design. The owner or homeowners' association decides, under the community's declaration and bylaws.
Private doesn't always mean outside traffic law. The national standard for signs, signals and markings covers any road open to public travel, including shopping-center roads, but not gated private communities.6 Some states also let private communities opt in to public enforcement. In Florida, an HOA board can vote by majority to have local police enforce state traffic law on its private roads. The roads stay private.7
Not sure which you have? Some states publish ownership lookups. Maryland's lets you search a road by name and see who maintains it.8 Otherwise, call your public works department and ask.
3. Which government has authority?
Start with ownership. It varies more than most people expect. As of 2012, South Carolina's state government owned 63 percent of the state's roads; New Jersey's owned 6 percent.3 A road that looks like a city street may belong to the state.
Then check who controls each piece. On one stretch of road, the signal, the pavement and the sidewalk can each belong to someone different. Washington's signal rule is one example.4 In Los Angeles, the owner of a lot maintains the sidewalk in front of it.9
Check for overlapping sovereignty. Where a Washington state highway crosses reservation land, the tribe can change the speed limit after an engineering and traffic study. The change takes effect only once the state approves it and signs go up.10
Ask each authority for its piece. One call rarely covers a request two governments share.
If the answers keep getting stranger, your area may be one of the documented exceptions. See When Jurisdiction Doesn't Follow the Pattern.
Once you know which government it is, look up its website and request channels in the Road Agency Directory.
4. How does that government process it?
| Track | When it applies | Who decides | What to bring |
|---|---|---|---|
| Service request | Restoring something already approved | Maintenance staff | Location, a photo, what's broken |
| Engineering study or warrant | Adding or changing a sign, signal or marking | Traffic engineer, under the state's MUTCD6 | Location and what you've seen: near misses, crossings, crashes |
| Capital project | Cost beyond routine maintenance | Local government; with federal money, also the MPO1112 | A sponsor: a council member or department |
| Legislative or public hearing | Changes the law treats as significant | An elected or appointed board13 | Testimony at the hearing |
| Adopted-plan implementation | The change is already named in an adopted plan | Staff, folded into scheduled work14 | The plan page that names your street |
| Compliance-triggered work | The law requires it when other work happens | Nobody; it's required5 | Nothing. Watch the project schedule. |
| Accessibility request | A barrier for people with disabilities | A separate accessibility program, where one exists9 | A description of the barrier |
Warrants protect the signs that matter. The Manual on Uniform Traffic Control Devices (MUTCD) is the national standard for signs, signals and markings. States adopt it as is, add a supplement, or write their own manual in substantial conformance.6 A warrant is proof of need, before the device goes in. Compliance is poor at unwarranted stop signs, they can raise speeds between intersections, and removing them has improved compliance at the stop signs that are justified.15
Not everything follows the MUTCD. Speed humps count as pavement design, not traffic control devices, so the MUTCD doesn't cover them.16 Each city writes its own rules. Pittsburg, California, for example, requires signatures from 67 percent of households on the street before its council will consider one.17 Treat any number you find as your city's rule, not a national one.
Intersections may get a formal comparison. An Intersection Control Evaluation compares options; a Road Safety Audit examines an existing site. See Decision & Evaluation Processes.
Federal money runs through the MPO. A project using federal highway or transit funds must appear in the region's Transportation Improvement Program, a four-year list adopted by the Metropolitan Planning Organization.11 Local public agencies apply and commit local money; residents comment.12 For other funding, see Funding & Financing Mechanisms. For building in stages, from pilot to permanent, see Construction Methodology & The Build Spectrum.
Small changes can need a vote. In San Francisco, adding or removing a midblock crosswalk takes a public hearing and action by the SFMTA Board.13
Resurfacing is the moment. Sacramento uses its bikeway plan to decide which streets get bike lanes when they're repaved.14 Resurfacing also triggers curb ramps under the ADA. Painting, crack sealing and patching don't.5
When jurisdiction gets strange
In Baltimore, the city maintains every road, including the interstates and numbered state routes, except three toll roads run by the Maryland Transportation Authority.8 The state highway agency maintains none of the city's roads.18 A route number won't tell you whom to call.
In parts of Colorado, a new subdivision's streets may be paid for by a metropolitan district: a local government with its own elected board, property tax and bonds, often set up by the developer before the first homes are built.19
These are real, documented structures, and there are more. When Jurisdiction Doesn't Follow the Pattern covers them.
Fair questions
My neighbors all agree. Why do we still need a study? Because the study asks a different question: will the device work? Drivers ignore signs they see as unneeded.15 In Kansas City the council can overrule the engineers,1 but that is a political fight, not a shortcut.
Can we take our project straight to the MPO? No. MPO funding goes to local public agencies, which apply and put up local money. Residents comment.12 Your first stop is the city or county that would sponsor it.
Is a decision final? Not always. In December 2025, a Queens judge ordered New York City to undo a half-built protected bike lane on 31st Street in Astoria. She found the city hadn't shown it met legal requirements to notify the fire department and other agencies.20 The city appealed.21 In April 2026, it restarted the approval process with those certifications in hand and a longer, 2.5-mile plan.22 A decision can fall on process, and a process can be redone.
Why did a curb ramp appear when nobody asked? Because the street was resurfaced. The ADA requires ramps whenever a street is altered that way.5
What you can do
- Name your request. Restore, add, or change the standard.
- Find the owner. Use an ownership lookup or call public works. Ask who maintains the road and who controls its signs and signals. The Road Agency Directory lists where to reach each agency.
- File it where it's tracked. Use 311 or the formal request channel, and keep the reference number. Kansas City's advice is not to skip this step.1
- Ask what the decision turns on. A warrant, a petition, a count? Get the criteria in writing.
- Check for scheduled work. Ask whether the street is due for resurfacing or named in an adopted plan.
- Use the right channel for access barriers. Ask whether your city runs a separate accessibility program.9
- If the answer is no, ask why. Ask which rule applied. Your council member can help move a request that stalls.1
Related Media
The items below come from outside the Commonway System, external videos, podcasts, and articles related to this page's topic, not part of the guidebook itself.
3 items
- Aligned
States Looking to Sell Some Roads to Cities and Towns
GoverningDaniel C. Vock explains which level of government owns which roads and how that ownership determines who can change a street, with a Beaufort, SC example of a city blocked from narrowing lanes on state-owned streets. It directly answers the Commonway System's core question of who has authority over a specific road.
MED-084 - Aligned
Talking Headways Podcast: Lessons from Quick-Build Street Projects
Talking HeadwaysJeff Wood interviews Smart Growth America's Heidi Simon on how local governments and advocates work through state DOT permitting to change streets via quick-build projects. It matches the Commonway System's "how governments process requests" section as a general process discussion rather than one city's project.
MED-088 - Context only
The Insane Ways Traffic Engineers Try to Make Streets 'Safe' For Walking
CityNerdRay Delahanty examines whether pedestrian crossing devices like RRFBs and HAWK signals actually work and how engineers decide when and where to install them. It covers the engineering decision process behind crosswalk requests, one of the Commonway System's named examples of changes residents ask for.
MED-077
References
- Precedent-based Merchant, Josh. "How to Request a Crosswalk, Speed Hump or Stop Sign in Kansas City." The Beacon, November 18, 2024.
- Precedent-based "Kansas City Traffic Deaths Keep Going Up, While Its Effort to Make Roads Safer Is Underfunded." KCUR, January 2, 2024.
- Precedent-based Vock, Daniel C. "States Looking to Sell Some Roads to Cities and Towns." Governing (Stateline), April 10, 2014. Ownership shares are 2012 Federal Highway Administration data.
- Legal / regulatory Revised Code of Washington 47.24.020(13), (17).
- Legal / regulatory U.S. Department of Justice and U.S. Department of Transportation. Joint Technical Assistance on the Title II of the Americans with Disabilities Act Requirements to Provide Curb Ramps when Streets, Roads, or Highways are Altered through Resurfacing. July 8, 2013.
- Legal / regulatory Standards. 23 C.F.R. § 655.603. Supplementary: Hawkins, Gene. "What You Need to Know About the New MUTCD." Kittelson & Associates, March 19, 2024.
- Legal / regulatory Florida Statutes § 316.006(2)(b)4 and (3)(b)5.
- Precedent-based Maryland Department of Transportation. "Know Your Roads."
- Precedent-based City of Los Angeles. "Access Request Program: Frequently Asked Questions."
- Legal / regulatory Revised Code of Washington 46.61.480 (2009 c 383 § 1).
- Legal / regulatory Planning Assistance and Standards. 23 C.F.R. Part 450, §§ 450.104 and 450.326.
- Precedent-based Indianapolis Metropolitan Planning Organization. "Indianapolis Regional Transportation Improvement Program."
- Precedent-based San Francisco Better Streets. "Crosswalks."
- Precedent-based Pedestrian and Bicycle Information Center. "Complete Streets Implementation in Sacramento." 2011.
- Evidence-based Bretherton, W. Martin, Jr. "Multi-way Stops: The Research Shows the MUTCD Is Correct!" Appendix A to All-Way Stop Control Warrant Study: E. Oakland St. & Merlot Dr. Rapid City Public Works, February 8, 2012.
- Evidence-based Smith, Duane E., and Karen L. Giese. A Study on Speed Humps. Ames: Center for Transportation Research and Education, Iowa State University, 1997.
- Precedent-based City of Pittsburg, California. Traffic Calming Policy. Adopted June 4, 2001; revised May 17, 2004. The policy may have been revised since.
- Precedent-based Maryland Department of Transportation State Highway Administration. Roads and maintenance.
- Legal / regulatory Colorado Division of Local Government. "Special Districts: A Brief Review for Residents." Summarizes C.R.S. Title 32, Article 1.
- Precedent-based Meyer, David. "Queens Judge Orders City to Nix Half-Installed Queens Bike Lane." Streetsblog NYC, December 5, 2025.
- Precedent-based "City Appeals Astoria Bike Lane Injunction." Queens Chronicle, January 2026. The article shows no date; month from its own reference to the December 5 ruling and appeal deadline.
- Precedent-based "Mamdani's DOT Responds to Astoria Bike Lane Backlash ... With an Even Longer Bike Lane." Streetsblog NYC, April 15, 2026.